470 KWp Solar Project
Janata Jute Mills Ltd.
Project Details
Date Installed: 1-April-2022
Capacity: 470 KWp.
Annual Energy Generation: 600.425 MWp.
CO2 Reduction: 425.44 tons per year.
Expected ROI: 3.9 years.
Client: Janata Jute Mills Ltd.
Location: Faridpur
Completed on 1 April 2022, this 470 KWp solar installation was delivered by Cynergy Limited for Janata Jute Mills Ltd. in Faridpur. The system is projected to generate approximately 600.43 MWh of clean energy annually, reducing CO2 emissions by around 425.44 tons per year, with an expected payback period of 3.9 years.
Learn more about our solar EPC services or read why jute mills in Bangladesh are switching to solar power.
Janata Jute Mills is also home to Cynergy’s 758.4 kWp floating solar installation and 8.35 MWh battery energy storage system (BESS) — Bangladesh’s first large-capacity BESS.